The roof went up on March 30th. It took about four hours to go from the fist crane lift to the roof as shown in the last picture.
March 26th
March 30th
Stay tuned, more to come…
Not really, we just like the name…
Note: click your pointing device (usually a mouse) on the thumbnails below to view a full size image.
March 18th, 7:38 AM
I-Beams – unlike the McMansion that was built next door to me, the main support beams will be steel rather than composite wood. You can also see the crew finishing up the water supply and sewer connections.
March 22nd, 11:08 AM
The following picture was taken during the positioning of support beams for the outer walls of the first floor. They were anchored using bolts that were sunk into the concrete when the basement was poured.
March 22nd, 5:55 PM
The following pictures show the results of the carpentry work for the day. I think there were four carpenters plus the crane operator working on site.
Note the cutout for the basement stairway in the following picture.
I think this is where the utility hookups will be.
You can see a portion of an I-Beam in the following picture.
The site at the end of the work day.
March 23rd
The site at the end of the work day .
March 25th
The site at the end of the work day.
That’s all for this week. More to come in future.
March 15th and 16th were spent preparing the garage and basement for the pouring of their concrete floors. For the garage, a large part of this was dumping fill to bring the floor to ground level. For the basement, this included the plumbing for the water supply, the sewer drains and the sump pump.
On March 17th, the garage floor was the last pour of the day. The concrete pumper was here earlier in the day to pour the basement floor.
The following pictures were taken after the end of the work day on March 17th. They show the finished basement and garage floors. The roughed in plumbing for the sewer drain, sump pump and water supply are also visible.
Note that all the roughed in plumbing is PVC rather than copper or cast iron.
This view shows the basement below-ground entrance. The depressions in the floor are footers for support beams.
This is the sewer drain ready to be hooked up to the town’s sewer system. Look closely and you can see a wire running along the drain pipe. Since the pipe is PVC rather than cast iron, the wire provides a magnetic source to locate the drain pipe once the trench is filled in.
That’s all for now…stay tuned for more…
Note: click your pointing device (usually a mouse) on the thumbnails below to view a full size image.
At 8:30 AM on March 5th, a crew showed up and started putting the forms for the basement walls in place. It took about 1.5 days for all the forms to be put in place and ready for the concrete pour.
Early in the morning on March 8th, the Concrete Pumper Truck was back in action again as was a herd of Concrete Mixer Trucks.
A steady stream of Concrete Mixer Trucks pulled up to the pumper as the pouring of the basement walls proceeded.
The pouring of the basement walls was done before noon. This included the finishing work such as putting in the anchor bolts for the house framing. I don’t know how many truckloads of concrete were used. I stopped counting after six.
Here are some pictures of the finished product. The forms were taken off and hauled away early this week. And then the rains came so not much else has been done. I think the plumber is up next to hook up the sewer lines and install a sump pump. Sump pumps are more or less standard equipment in all houses both old and new in this area.
Stay tuned for more…
Note: click your pointing device (usually a mouse) on the thumbnails below to view a full size image.
Yesterday morning , the last load of dirt was hauled away and shortly thereafter, the excavator was loaded onto a flatbed trailer and hauled away. Around noon, a crew showed up and began building forms for the basement footer.
Around 7:30 this morning, a Concrete Pumper Truck appeared. A short while later, Concrete Mixing Trucks showed up and the crew started pouring concrete.
I don’t now exactly what time they finished the basement footer, but by 11:30 AM, all activity had ceased
Stay tuned for more….
Note: click your pointing device (usually a mouse) on the thumbnails below to view a full size image.
The demolition phase of our neighborhood’s latest suburban renewal project started promptly at 7:45 AM Monday, February 28th.
By 9:08 AM, about 50% of the house was gone.
At 10;23 AM, all that remained was a pile of rubble.
After lunch and a rain delay, the rubble was loaded onto trucks for transit to the local land fill.
Two truckloads of rubble were hauled away by 4:00 PM.
You can see a larger version of this video on YouTube.
Stay tuned for more.